Time for another update...It's June 2003, we've completed fixing the bottom
three layers of the hull & we're half way through fixing the plywood to the hull
sides. We have accomplished alot in the last 6 months & it's very encouraging to
see an end in sight. At least if it is only the hull.
First sheets of ply being screwed & epoxied
to the stringers along the hog.
Coming forward with ply sheets along the
chine.
Now to the first layer on the other side.
A long shot.
All three layers on the bottom sides.
A picture of our clamping system.
We are quite happy with the fair at this
stage.
Rear shot.
Transom plywood fixed. (3 layers)
And the other side of the transom.
We expect to be finished fixing all of the plywood in the next 2 to 3 months.