Here is a brief update of progress for the start of the new year. We have completed the bulwark framing & glassing, all that is left now is the bulwark cap & to cut the transom door. We have also started work on the forward accommodations as you can see below.
Below you will see our progress to the end of January. The forward accommodation framing is progressing well & should be completed in the next month. You will notice the plywood in the floor of the shower has been profiled to fall towards the drain which shows the glue lines in the ply. Also we have commenced fitout in the engine room. Installing the fuel lines & filters, hot & cold water lines, saltwater intake manifold & associated pumps.